Familiarize yourself with the protection relay and its functionality before you start the
commissioning work.
Ensure that you have all the needed station drawings such as single line and wiring
diagrams.
Ensure that your version of the technical manual applies to the protection relay
version you test.
Ensure that your setting software and connectivity packages work with the protection
relay version you test.
Find out if you need any additional software.
Ensure that you have the relay settings either on paper or in electronic format. The
settings and logic should be well documented.
Inspect the settings to ensure that they are correct.
Ensure that you have the correct cable to connect your PC to the protection relay's
communication port. The RJ-45 port supports any CAT 5 Ethernet cable but the
recommendation is STP.
Test your PC's communication port before you go to the site.
Find out who to contact if you have trouble and make sure you have a means to contact
them.
Find out who is responsible for the settings.
Ensure that you have with you the proper test equipment and all needed connection
cables.
Ensure that the owner of the switchgear familiarizes you with the work site and any
special aspects of it.
Ensure that you know how to operate in emergency situations. Find out where the first
aid and safety materials and exit routes are.