Size G+control procedure: (Refer to Figure 3-3.)
Control Transformer
1.
Be sure drive operation is terminated and control is disabled.
2.
Remove all power sources from the control. If power has been applied, wait at
least 5 minutes for bus capacitors to discharge.
3.
Remove or open the front cover. Locate the control transformer fuse block
(see Figure 3-1).
4.
Remove the wires from the two right side terminals (460VAC connection).
5.
Place the wires on the center terminals as shown (380VAC connection).
6.
Install or close the front cover.
460VAC
Connection
For Fuse Block, location refer to Figure 3-1.
380-400VAC
Connection