Prerequisites

It is recommended to attach the IOTA board to the carrier prior to mounting the module to the
IOTA. The following also needs to be established:
IOTA is mounted on the carrier rack.
Power supply is installed.
All wiring and pre-fabricated cables are available and labeled as applicable.
Ensure all power is turned off at the installation location.
You have the mounting hardware supplied with the components.

Mounting the module

Step
1
Insert the module onto IOTA board ensuring that the circuit board mates
properly with the IOTA board connector.
2
Secure the module to the IOTA board - with two screws located at each side
of the plastic cover.
R500
April 2017
3. Series 8 I/O Installation and Upgrades
3.4. Mounting the I/O module on the IOTA
Action
Series 8 I/O User's Guide
Honeywell
45

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents