4. Installation
4.7
Electrical connections
36
2. Fit together the combustion gas exhaust pipes, without welding.
The pipes must allow no leakage of flue gases and be
4
resistant to corrosion.
Connect the pipes together without stress between
4
the sections.
Maximum bracket distance from vertical pipes is 2 m.
4
Maximum tilt of vertical pipes is 20 mm/m.
4
The pipes must not rest on the boiler or flue gas
4
adapter.
The horizontal sections need to be constructed with a
4
gradient of 50 mm per metre: Back to the boiler.
Use a bracket at each connection from horizontal
4
pipes.
4.6.6.
Connection of the air intake pipe
Mounting
1. Fit the air-intake conduit.
2. Fit the air-intake conduits together without welding.
The pipes must be airtight and corrosion-resistant.
4
Connect the pipes together without stress between
4
the sections.
Maximum bracket distance from vertical pipes is 2 m.
4
Maximum tilt of vertical pipes is 20 mm/m.
4
The pipes must not rest on the boiler or air supply
4
adapter.
The horizontal sections need to be constructed with a
4
gradient: Downwards in the direction of the supply
opening.
Use a bracket at each connection from horizontal
4
pipes.
Material
Single wall, rigid
Flexible
(1) The materials used must comply with the prevailing regulations and standards
For the connection(s) of the boiler Gas 610 ECO PRO: The
features and instructions described are for each boiler
module.
Gas 310 ECO PRO - Gas 610 ECO PRO
aluminium/Stainless steel
160514 - 125467-05
(1)