Commissioning And Startup - Siemens SIMATIC ET 200pro Manual

Distributed i/o ethernet/ip interface module
Hide thumbs Also See for SIMATIC ET 200pro:
Table of Contents

Advertisement

Commissioning

5.4 Commissioning and startup

5.4
Commissioning and startup
You commission the automation system according to your plant configuration. The
procedure outlined below only describes the commissioning of ET 200pro connected to an
EtherNet/IP master.
Requirements of ET 200pro on EtherNet/IP
References to chapters in the following table are to the "SIMATIC ET 200pro distributed I/O
system Operating Instructions" manual. You can access the manual on the companion disk
that shipped with your product. You can also access the manual on the Siemens Industry
Online Support (https://support.automation.siemens.com/cs/?lc=en-US) website.
For I/O controller actions, reference the manual that shipped with your I/O controller.
Actions
ET 200pro is mounted
ET 200pro is wired
Device names are assigned to the I/O device
ET 200pro is configured
Supply voltage to the I/O controller is switched on
I/O controller is in RUN
Commissioning the ET 200pro system
1. Switch on the electronic / encoder supply 1L+ for ET 200pro
2. Switch on the load voltage supply(ies) 2L+
Note
Changes to the backplane bus
Always switch off power to the electronic / encoder supply 1L+ before you modify the
backplane bus configuration (for example, changing the number of modules, removing the
terminating module).
Commissioning the ET 200pro EtherNet/IP
1. Switch on the supply voltage for the module
2. Switch on the supply voltage for the load as necessary
58
Reference
Chapter "Mounting"
Chapter "Wiring"
Chapter "Configuring"
Chapter "Configuring"
I/O controller manual
I/O controller manual
ET 200pro distributed I/O EtherNet/IP interface module
Manual, 03/2016, A5E32861915-AB

Advertisement

Table of Contents
loading

Table of Contents