116 Electrical installation

Connection procedure (US)

WARNING! Apply grease to stripped aluminum conductors before attaching them
to non-coated aluminum cable lugs. Obey the grease manufacturer's instructions.
Aluminum-aluminum contact can cause oxidation in the contact surfaces.
1. Do the steps in section
the work.
2. Open the cabinet door.
3. Open the swing-out frame (if installed).
4. Plan cable access and mark the conduit plate accordingly for the input and output
power and control cables.
5. Remove the conduit plate from the drive cabinet and cut holes as needed for the
conduit connections. Note: Never cut metal in or around an equipment cabinet. Metal
debris can cause damage to electrical equipment and hazardous conditions.
6. Reinstall the conduit plate to cabinet and connect all electrical conduits as needed to
conduit plate. Do not leave any open holes at the top of the cabinet.
7. Run the motor power cables and separate ground cable (if present) from the motor to
cabinet.
8. Connect the motor power cable shields and separate ground cable (if present) to the
ground bar at the top of the cabinet.
9. Connect the motor phase conductors to the output power terminals U2, V2 and W2.
10. For drives with external brake resistors (option +D150 and no +D151):
Run the power cables from the brake resistor to the cabinet including the proper
grounding cable.
Connect the ground cable to the ground bar at top of cabinet.
Connect the brake resistor power cables to the R- and R+ terminals.
11. Make sure that all power is disconnected and reconnection is not possible. Use proper
safe disconnect procedures according to local codes.
12. Run the AC power supply cables and separate ground cables (if present) from the
supply source to the cabinet.
13. Connect AC power supply cable shields and separate ground cables (if present) to the
ground bar at top of cabinet.
14. Connect AC supply phase conductors to terminals L1, L2 and L3.
15. Reinstall the shroud(s) and mounting plates.
Precautions before electrical work
on page
18
before you start