ABB TPL85-B14 Operation Manual page 68

Hide thumbs Also See for TPL85-B14:
Table of Contents

Advertisement

Operating the wet
cleaning system
© Copyright 2016 ABB. All rights reserved.
Maintenance
Cleaning turbine blades and nozzle ring
in operation
Wet cleaning
1 Water supply (fresh water only)
2 Regulating valve
3 Manometer
5 Stainless-steel piping
6 Other turbochargers
7 Injection nozzle item 7a or 7b
Before cleaning, the Operating state prerequisites for wet cleaning
must be met.
Check that the water supply (1) is open and safeguarded and that it is
also connected to the regulating valve (2) before the turbocharger.
Set drain cock (9) of drain pipe (8) on gas outlet casing to Position 1
and check whether exhaust gas escapes.
Quickly open regulating valve (2) until manometer (3) indicates follow-
ing pressure: injection nozzle (7a) 1 ± 0.2 bar or injection nozzle (7b)
3 ... 3.5 bar.
Inject water for 5 minutes (injection nozzle 7a) or 10 minutes (injection
nozzle 7b) at constant engine output.
Check whether the exhaust gas temperature decreases following the
turbine.
Operation Manual / TPL85-B14/-B15/-B16
5
5.5
8 Drain pipe
9 Drain cock
10 Drain
11 Orifice (integrated into turbocharger)
21 Air line from the compressor casing
A Position 1
B Position 2
Page 66