INSTALLATION
3.
NOTE A separate contact must simultaneously cause UPS input AC power to be removed.
4.
5.
6.
7.
8.
18
EATON Powerware
Connect isolated, normally-open, dry contacts (rated to handle
60 Vdc maximum, 30 Vac RMS maximum, and 20 mA maximum)
across the REPO device to Pin 1 and Pin 2 (see Figure 15).
Use stranded, non-shielded wiring, size 0.75 mm
(18–20 AWG).
Reconnect the REPO connector to the REPO port.
Verify that the externally-connected REPO switch is not activated to
enable power to the UPS output receptacles.
Plug in the UPS and start the UPS by pressing the On button for
approximately three seconds.
Activate the external REPO switch to test the REPO function.
De-activate the external REPO switch and restart the UPS.
®
5125 (9910-E65) UPS Installation Guide for IBM
Pin 1
Pin 2
Figure 15. REPO Connector
®
S
Applications
164201698 Rev 1
2
2
–0.5 mm