Filling The Condensate Trap; Gas Connection - REMEHA CALORA TOWER GAS 15S EX Installation And Service Manual

Floor-standing high efficiency gas boiler
Table of Contents

Advertisement

CALORA TOWER GAS 15S EX CALORA TOWER GAS 25S EX
CALORA TOWER GAS 35S EX
2
3
5
4
6
6
5.6

Gas connection

22/04/2016 - 300026141-001-07
5.5.6.
1. Remove the siphon.
2. Fill the siphon with clean water up to the mark.
3. Re-assemble the siphon.
1
L000181-A
C003098-E
1. Connect the gas inlet pipe.
2. Fit a gas stop valve to this pipe in such a way that it is visible and
easily accessible.
3. Connect the gas pipe to the gas shut off valve.
1
M002525-A

Filling the condensate trap

CAUTION
Fill the condensate trap with water before starting the
boiler to avoid combustion products escaping from the
boiler.
DANGER
Before making the gas connections, ensure that the boiler
is immobilised in accordance with prevailing standards.
WARNING
Close the main gas valve before starting work on the
4
gas pipes.
Before mounting, check that the gas meter has
4
sufficient capacity. To do this, you should keep in
mind the consumption of all domestic appliances.
If the gas meter has a too low capacity, inform the
4
energy supply company.