5. Installation
30
5.5.5.
1. Mount a standard drainage pipe, Ø 32 mm or more, leading to the
mains drainage system.
2. Into this, insert the condensate collector hose coming from the
siphon j .
3. Mount a trap or a siphon in the discharge pipe.
1
M002535-A
CALORA TOWER GAS 15S EX CALORA TOWER GAS 25S EX
On an installation in which the flow can be fully
disconnected from the return (e.g. by using thermostatic
valves), a bypass should be fitted or the expansion vessel
placed on the heating flow pipe.
Connecting the condensate discharge pipe
CAUTION
Do not make a permanent rigid connection owing to
maintenance work on the condensate trap.
Do not plug the condensate discharge pipe.
4
Set the discharge pipe at a gradient of at least 30 mm
4
per metre, maximum horizontal length 5 metres.
Do not drain condensation water into a roof gutter at
4
any time.
Connect the condensate discharge pipe in
4
accordance with prevailing standards.
CALORA TOWER GAS 35S EX
22/04/2016 - 300026141-001-07