Unit Assembly Prior To Installation; Venting Introduction - Regency PANORAMA P33E Owners & Installation Manual

Hide thumbs Also See for PANORAMA P33E:
Table of Contents

Advertisement

installation
|
16

UNIT ASSEMBLY PRIOR TO INSTALLATION

The Top Facing Support, the Side Nailing Strips and
the 2 Top Standoffs must be correctly positioned and
attached to the top before the unit is put into position.
Top Standoff Assembly
The top standoffs are shipped in a flat position and
must be pulled up and bent into the correct shape.
1) Remove the standoffs from on top of the firebox
by undoing the screws.
2) Take each standoff and bend into the correct
shape. Bend up at the bend lines until the screw
holes in the standoff and the pre-punched screw
holes on the firebox top line-up.
3) Attach the standoffs securely to the top with 4
screws per standoff.
Note: Secure the standoffs to the holes closest
to the edge of the firebox top.

VENTING INTRODUCTION

The P33-10 uses the "balanced flue" technology Co-Axial system. The inner liner vents products of combustion to the outside while the outer liner draws
outside combustion air into the combustion chamber thereby eliminating the need to use heated room air for combustion and losing warm room air up the
chimney.
There are 5 vent systems approved for use with the P33-10: the Regency
Vent, Selkirk Direct-Temp, Amerivent Direct Vent and Security Secure Vent Systems for Horizontal and Vertical Terminations (see following "Venting" Sections
for more details).
Note: These flue pipes must not be connected to any other appliance.
The gas appliance and vent system must be vented directly to the outside of the building, and never be attached to a chimney serving a separate solid fuel
or gas burning appliance. Each direct vent gas appliance must use it's own separate vent system. Common vent systems are prohibited. (See "Rigid Pipe
Venting System" for more details and exceptions).
NOTE: Ensure compliance with the outside vent terminal location before cutting hole as both dimensions must be met.
16 |
Regency® P33E-10 Zero Clearance Direct Vent Gas Fireplace
Top Facing Support &
Side Nailing Strips
Determine the total thickness of facing material
(e.g. drywall plus ceramic tiles) to allow the finished
surface to be flush with the front of the unit. Total
facing thickness can vary from 1/2" (13mm) to
1-1/4" (32mm) thick.
The Top Facing Support & Side Nailing Strips can
be mounted in various positions depending on the
thickness of the facing material.
1) Mount Top Facing Support using the 3 supplied
screws into the three pre-punched screw holes
on the top front of the unit. Adjust support to
desired facing material depth.
2) Mount Side Nailing Strip using the 3 supplied
screws into the three pre-punched screw holes
at the front sides of the unit. Adjust support to
desired facing material thickness.
For a facing material depth of
1-1/4"(32mm), the top facing
support must be reversed.
Direct Vent Flex System for Horizontal Terminations only and the Simpson Dura-
®
NOTE:
If finishing flush with the VIgnette Finishing Trim -
remove top nailing strip (facing support) if already
installed and use the nailing strip supplied with
the Trim.
Nailing strip
supplied with
trim
Top Facing
Support
If finishing flush with the VIgnette Finishing Trim
-bend nailing strips around side trim pieces as
shown below.
Side
Nailing
Strips
(folded out)

Advertisement