IDEAL VOGUE SYSTEM S15 Installation And Servicing page 14

Hide thumbs Also See for VOGUE SYSTEM S15:

Advertisement

3
Sy Ste M b Al An Cin G
The boiler does not normally need a bypass but at least some radiators on the heating circuit, of load of at least 10% of the
minimum boiler output, must be provided with twin lockshield valves so that this minimum heating load is always available. See
note regarding thermostatic radiator valves on page 11.
n ote. Systems incorporating zone valves which could completely cut off the flow through the system must also include a bypass.
bA l An Cin G
1. Set the programmer to ON.
Close the manual or thermostatic valves on all radiators, leaving the twin lockshield valves (on the radiators referred to above)
in the OPEN position.
Turn up the room thermostat and adjust the lockshield valve to give an uninterrupted flow through the radiator.
These valves should now be left as set.
2. Open all manual or thermostatic radiator valves and adjust the lockshield valves on the remaining radiators, to give around
20
o
C temperature drop at each radiator.
3. Adjust the room thermostat and programmer to NORMAL settings.
4
WAte R t Re At Ment
Cent RAl He Atin G
The Vogue range of boilers have a stainless steel heat
exchanger.
iMPo Rt Ant.
The application of any other treatment to this product may
render the guarantee of Ideal Boilers Invalid.
Ideal Boilers recommend Water Treatment in accordance with
the Benchmark Guidance Notes on Water Treatment in Central
Heating Systems.
If water treatment is used Ideal Boilers recommend only the
use of
SCALEMASTER GOLD 100, FERNOx, MBI, A DEY MC1
inhibitors and associated water treatment
or SENTINEL x 100
products, which must be used in accordance with the
manufacturers' instructions.
n otes.
1. It is most important that the correct concentration of the water
treatment products is maintained in accordance with the
manufacturers' instructions.
2. If the boiler is installed in an existing system any unsuitable
additives MUST be removed by thorough cleansing. BS
7593:2006 details the steps necessary to clean a domestic
heating system.
3. In hard water areas, treatment to prevent lime scale may be
necessary - the use of artificially softened water is permitted
when filling the system, where the cold supply is fitted with a
water softening device.
4. Under no circumstances should the boiler be fired before the
system has been thoroughly flushed.
14
GeneRAl
For further information contact:
Fernox Cookson Electronics
Forsyth Road, Sheerwater, Woking, Surrey GU21 5RZ
+44 (0) 8706 015000
Sentinel Performance Solutions
The Heath Business & Technical Park
Runcorn, Cheshire WA7 4Qx
Tel: 0800 389 4670
Scalemaster Water Treatment Products
Emerald Way, Stone, Staffordshire ST15 0SR
Tel: +44 (0) 1785 811636
Calmag Ltd.
Unit 3-6, Crown Works, Bradford Road,
Sandbeds, Keighley, West Yorkshire BD20 5LN
Tel: +44 (0) 1535 210320
Adey Professional Heating Solutions
Gloucester Road, Cheltenham GL51 8NR
Tel: +44 (0) 1242 546700
vogue system boiler -
Installation and Servicing