boile R di Men Sion S, Se RViCe S & Cle ARAn Ce S
The boiler connections are made on the boiler connection tails.
Refer to Frame 28.
The following minimum clearances must be maintained for
operation and servicing.
Additional space will be required for installation, depending
upon site conditions.
Side and Rear Flue
a. Provided that the flue hole is cut accurately, e.g. with a core
drill, the flue can be installed from inside the building where
wall thicknesses do not exceed 600mm (24"). Where the
2.5
450
51 37.5
12
2.5
from case
Side flue
dim. A
132
132
50
42.5
GeneRAl
space into which the boiler is going to be installed is less
than the length of flue required the flue must be fitted from
the outside.
Installation from inside ONLY
b. If a core boring tool is to be used inside the building the
space in which the boiler is to be installed must be at least
wide enough to accommodate the tool.
445
740
f ront clearance
The minimum front clearance when built in to a cupboard is 5mm
from the cupboard door but 450mm overall clearance is still
required, with the cupboard door open, to allow for servicing.
*
b ottom clearance
Bottom clearance after installation can be reduced to 5mm.
This must be obtained with an easily removable panel, to enable
the consumer to access the filling loop, and to provide the 100mm
clearance required for servicing.
vogue system boiler -
all dimensions in mm
330
Installation and Servicing

Hide quick links:

Advertisement

loading

This manual is also suitable for:

Vogue system s18Vogue system s26Vogue system s32