Whole Unit Assembly
The assembly process is divided into sub-assembly and main assembly.
Perform the sub-assembly first to construct each unit from the parts. Then proceed to the main
assembly.
When assembling the printer, check each part and its attachment position by referring to the
exploded diagrams in Chapter 6.
For adjustments, follow the descriptions at the end of this chapter. Whenever disassembly is
performed even for just one part, check whether adjustment is necessary before assembly.
Sub-assembly
Sub-assembly A: N.E. Detector-J Assembly and N.E. Detector-R Assembly
1. Place protrusions
2. Align the U-shaped grooves with dowels
Rev. A
of the lever-N.E. detector onto sections
b
direction of the arrow with protusions
TM-U950/U950P Technical Manual
of the holder-N.E. detector.
a
by turning the lever-N.E. detector in the
c
as the center.
a
Disassembly, Assembly, and Adjustments 5-65