4. Open the power supply latch on the new supply by pressing the thumb
release and opening the latch. Install the new hot-plug power supply in
your open area. Push the hot-plug power supply into the slot 1 and
swing the arm into the locking position 2.
2
Figure 3-41. Installing a hot-plug power supply
5. Plug the power cord into the new hot-plug power supply.
NOTE: When installed properly, the LED on the back of the power supply unit is green. If
the LED is off, the unit is faulty, the server is in Standby mode, or the power cord is not
plugged in.
Figure 3-42. Plugging in the power cord