Switch Memory and Configuration
Using Primary and Secondary Flash Image Options
Scheduled Reload. Additional parameters have been added to the reload
command to allow for a scheduled reboot of the switch via the CLI.
Syntax: [no] reload [after <[dd:]hh:]mm> | at <hh:mm[:ss]> [<mm/dd[/[yy]yy]>]]
The scheduled reload feature removes the requirement to physically reboot
the switch at inconvenient times (for example, at 1:00 in the morning). Instead,
a reload at 1:00 mm/dd command can be executed (where mm/dd is the date
the switch is scheduled to reboot).
N o t e
Configuration changes are not saved with reload at or reload after commands.
No prompt to save configuration file changes is displayed. See Table 6-2 on
page 6-19.
Examples of scheduled reload commands:
6-22
Enables a scheduled warm reboot of the switch. The switch boots
up with the same startup config file and using the same flash
image as before the reload.
Parameters include:
• after: Schedules a warm reboot of the switch after a given
amount of time has passed.
• at: Schedules a warm reboot of the switch at a given time.
The no form of the command removes a pending reboot request.
For more details and examples, see below.
To schedule a reload in 15 minutes:
ProCurve# reload after 15
To schedule a reload in 3 hours:
ProCurve# reload after 03:00
To schedule a reload for the same time the following day:
ProCurve# reload after 01:00:00
To schedule a reload for the same day at 12:05:
ProCurve# reload at 12:05
To schedule a reload on some future date:
ProCurve# reload at 12:05 01/01/2008