7
Boiler block assembly
Installing thermal insulation
Position the thermal insulation over the boiler block.
Push the thermal insulation below the boiler block in
the direction of the arrow.
Position the thermal insulation tabs in front of the top
tie-bar and draw them together with a spring clip.
Fitting the side panels
The side panels are fitted identically on each side (r.h.
side panel shown here)
Push the snap nut onto the angled sheet steel of the
side panel until it locks into the hole provided.
Push the side panel into the angled part of the bottom
cross bar.
30
Installation and maintenance instructions Logano G215 US oil/gas-fired boilers • Issue 11/2004
Fig. 37 Installing thermal insulation
1 Spring clip
2 Thermal insulation tabs
Fig. 38 Positioning snap nut (here: r.h. side panel)
Fig. 39 Push in the bottom front corner of the side panel
1 Angled part of the bottom cross bar
We reserve the right to make any changes due to technical modifications.