Step 5
Once the line cards have rebooted, check the "show stack_information" command in the CLI to verify all line cards are now
holding the same firmware version as the CPU. If there is a discrepancy in any line card, the user must again repeat the download
firmware process for the line cards in question.
Step 6
After confirming all firmware runtime codes are the same, the user must download the PROM code through a TFTP server.
Although the same PROM code is to be used for both line cards and the CPU, the user must download the PROM code to both the
CPU and the line cards separately. This may be done in any order preferable to the user but two downloads must take place, as
shown below.
DES-6500:4#download firmware_fromTFTP 10.48.74.121 c:/DES6500_PROM_B20.had unit all_line_card
Command: download firmware_fromTFTP 10.48.74.121 c:/DES6500_PROM_B20.had unit all_line_card
Connecting to server................... Done.
Download firmware.................... Done.
Connecting to slave...................Done.
Upload firmware........................Done.
Line card will automatically reboot after a few minutes. Please don't power off!
Success.
DES-6500:4#
DES-6500:4#download firmware_fromTFTP 10.48.74.121 c:/DES6500_PROM_B20.had unit cpu
Command: download firmware_fromTFTP 10.48.74.121 c:/DES6500_PROM_B20.had unit cpu
Connecting to server..................................... Done.
Download firmware...................................... Done. Do not power off!
Please wait, programming flash....................Done.
Saving current settings to NV-RAM...............Done.
Please wait, the switch is rebooting...