Monitoring Synchronous Unit Operation (CJ2H CPU Units with Unit Version 1.1 or
Later)
The operating status of synchronous unit operation can be monitored. The status of errors and warnings related
to sending and receiving synchronous refresh data can be displayed, along with the maximum and present values
for the synchronous processing time. This makes it possible to check whether synchronous unit operation is
functioning correctly, to check whether operation is within the set range for the synchronous operation cycle,
and to make adjustments.
For details on the Synchronous Operation Status Window, refer to the CJ2 CPU Unit Software Manual (Cat.
No. W473).
1, 2, 3...
PLC Program Assignments
The Project PLC Program Assignments dialog lists all tasks and their associated program names for the selected
PLC in the project. The list can then be printed.
Use the following procedure to print PLC program assignments.
1, 2, 3...
The set value that is changed here will not be updated in the Timings/Synchronous Tab Page
in the PLC Setup. To update the PLC Setup, transfer the PLC Setup to the personal computer.
1. Select PLC – Edit – Synchronous Operation Status.
The Synchronous Operation Status Dialog Box will be displayed to enable confirming the
status of synchronous unit operation.
1. Select the PLC object in the project workspace.
2. Select Program Assignments from the PLC menu.
3. Select the Print pushbutton to print the program assignments.
4. Select the Close pushbutton.