3-8 Removing covers and grilles
Procedure 3-4
Removing the top cap grilles
Use this procedure to remove the top cap grilles from modular business
package (MBP) master or expansion cabinets.
Requirements
Before beginning this procedure, you must remove the equipment cover
immediately below the top cap grille, as described in Procedure 3-1.
The following tools and materials are required:
•
Action
Step
1
2
3
AccessNode P0904244 Issue 1.0
sheets of cardboard or foam on which to rest the equipment covers while
the installation is being performed
Action
Push upward on the two plastic tabs that protrude below the casting as shown
in Figure 3-4.
Tilt the grille outward, and lift it up to remove it.
Store the grille on cardboard or foam to protect its finish while you perform the
installation.