Commissioning, inspection, maintenance

Fitting the burner (gas condensing module)

4x
F
D
C
B
A
Fig. 76
1. Insert the burner and tighten screws
Torque: 6.5 Nm
2. Fit gas supply pipe
E
Torque: 30 Nm
3. Check the gas connections for leaks.
Danger
Escaping gas leads to a risk of explosion.
Check the fitting for gas tightness.

Checking the neutralising system (if installed)

5-yearly maintenance of fuel cell module

Note
Before carrying out the maintenance work:
The fuel cell module must be in maintenance mode.
Start maintenance mode, see page 72.
The distilled water must have been drained.
82
E
F
diagonally.
with a new gasket.
4. Connect the cables/leads:
Fan motor
A
Ionisation electrode
Ignition unit
C
Earth
D
B