5.3 PHASE-TO-PHASE ZONE REACH TESTING
5.3 PHASE-TO-PHASE ZONE REACH TESTING
1. Protection Settings:
Z1DISTANCE
(101)
Z1PHASE = YES
(104)
Z1P_TIME = 0.0 sec.
Z2DISTANCE
(201)
Z2PHASE = NO
Z3DISTANCE
(301)
Z3PHASE = NO
Z4DISTANCE
(401)
Z4PHASE = NO
LINEINFO
(1204) TRSMFRTYPE = NONE
2. Connect the relay as shown in Figure 5–1: PHASE-TO-PHASE TEST CONNECTIONS on page 5–7 for
the appropriate phases under test. Set the relay to test mode 14 (Any Zone 1 Phase). The LUI displays:
ANY Z1 PHASE ON
5
3. Set the voltage inputs to the following values:
VA: 67 volts rms ∠0°,
VB: 67 volts rms ∠–120°,
VC: 67 volts rms ∠+120°.
4. Set the phase angle of the fault current I
PHASE SETTINGS FOR TEST T11. Note that the leading phase angle is 180° out of phase with the line to
which it is shorted.
Table 5–2: FAULT CURRENT PHASE SETTINGS FOR TEST T11
∠I Degrees
–25
–55
–85
Reference only
5. Set the fault current to 10.0 (2.0) amps rms. Reduce the voltage of the faulted phases and check that the
A1 contact closes when the voltages are within the limits shown in Table 5–2: FAULT CURRENT PHASE
SETTINGS FOR TEST T11.
6. Reduce the fault current to zero. Note that the trip target indication concurs with the fault. For example, an
AB fault is displayed as follows:
TRIP AB Z1 "DIST"
5-
10
to the phase-angle value listed in Table 5–2: FAULT CURRENT
op
Volts rms
Displayed Target
51 to 57
59 to 66
82 to 88
51 to 57
LPS-O Line Protection System
5 FUNCTIONAL TESTS (FACTORY SETTINGS)
5.3.1 T11 – ZONE 1 PHASE REACH TEST
GE Power Management