Reel Assembly Installation (continued)
Cutting Unit: Service and Repairs
g252671
1.
RH side plate
4. Apply a thin coat of antiseize lubricant to the reel bearing bore of each side
plate.
5. Make sure that flat wire spring (item 14) is installed into LH side plate.
Contact with the reel, bedknife or other cutting unit parts can result
in personal injury. Use heavy gloves when installing the cutting reel.
6. Carefully slide the RH end of the cutting reel assembly (no groove in reel
shaft or on face of threaded insert) into the RH side plate. Make sure that
bearing is fully seated into side plate.
7. Slide the LH side plate onto the cutting reel assembly.
8. Install shoulder bolts and flange nuts that secure the LH side plate to the
cutting unit frame. Tighten the shoulder bolts from 37 to 44 N∙m (27 to 33
ft‐ ‐ ‐ lbs).
9. Apply Loctite #243 (or equivalent) to threads of flange head screw that
secures frame spacer and carrier frame to LH side plate. Install screw and
tighten from 37 to 44 N∙m (27 to 33 ft‐ ‐ ‐ lbs). After tightening screw, check the
clearance between the carrier frame and side plate. If clearance is more than
0.065" (1.6 mm), remove flange head screw and position shim(s) between
carrier frame and side plate so that clearance is less than 0.065" (1.6 mm).
Make sure that the carrier frame pivots freely after assembly.
10. Install cap screw and flat washer that secure rear grass shield to LH side
plate. Torque screw from 20 to 25 N∙m (15 to 19 ft‐ ‐ ‐ lbs).
11. Install the rear roller; refer to
12. Install the front roller; refer to
Figure 344
2.
LH side plate
CAUTION
Installing the Rear Roller (page
Installing the Front Roller (page
Page 9–38
9–45).
9–43).
Reelmaster
®
5410/5510/5610 Series
15216SL Rev C

Advertisement

Table of Contents
loading

Table of Contents