Commissioning
9.2
Tests before the initial commissioning
A report that provides the configuration can be created with the Setting and Monitoring
Tool.
The purpose of the initial commissioning tests is to confirm the safety requirements
specified in the national/international rules and regulations, especially in the Machine
and Work Equipment Directive (EC Conformity).
Check the effectiveness of the protective device at the machine, using all the
selectable operating modes and functions.
Ensure that the operating personnel of the machine fitted with the safety controller
become instructed by the qualified personnel of the machine owner before
beginning work. Arranging the instruction is the responsibility of the machine owner.