Making Robot Ready For Operation (Foundry Prime); Additional Installation Procedure - ABB IRB 6640 - 180/2.55 Product Manual

Articulated robot
Table of Contents

Advertisement

2.8 Making robot ready for operation (Foundry Prime)

2.8.1. Additional installation procedure

General
Robots delivered with the Foundry Prime protection are specially designed to work in water
jet cleaning cells with 100% humidity and alkaline detergent. To ensure that the protection
offers the best reliability, some measures are needed during installation of the robot according
to the procedures below.
NOTE!
For best reliability, it is of highest importance that the special maintenance instructions for
the Foundry Prime robot are followed and documented.
Commissioning
Environmental conditions
The table below details the environmental conditions.
Parameter
Humidity
Washing detergent with pH
Washing detergent must contain rust inhibitor
and be approved by ABB
Cleaning bath temperature
Air specification for pressurizing of robot
The air must be dry and clean, such as instrument air. The table below details the air
specifications.
Parameter
Dew point
Solid particle size
Oil content
Pressure to robot
3HAC026876-001 Revision: C
Never switch off the overpressure in motors and serial measurement compartment
during cooling down of robot after it has been switched off.
When turning off a cleaning cell we recommend that the humid air inside a cell is
ventilated out, to avoid that the humid air is sucked into gearboxes for example, due
to the raised vacuum when cooled down.
2 Installation and commissioning
2.8.1. Additional installation procedure
Value
100%
<9.0
<60°C, used in a typical waterjet cleaning
application at suitable speed.
Value
<+2°C at 6 bar
<5 microns
<1 ppm (1 mg/m3)
0.2 - 0.3 bar