Installation Overview; Table 15: Installation Procedures - Allied Telesis AT-8100S/24C Installation Manual

Fast ethernet switches
Hide thumbs Also See for AT-8100S/24C:
Table of Contents

Advertisement

Chapter 3: Beginning the Installation

Installation Overview

62
Table 15 lists the installation procedures for a stack of 8100S Series
switches. The procedures should be performed in the order presented in
the table.
Table 15. Installation Procedures
Step
1
"Reviewing Safety Precautions" on page 63
2
"Planning the Installation" on page 67
3
"Unpacking the Switch" on page 69
4
"Installing the Switches in an Equipment Rack" on
page 72
5
"Labeling the Switches" on page 77
6
"Verifying and Setting the Stack ID Numbers" on page 82
7
"Cabling the Stacking Ports" on page 87
8
"Powering on AC Switches" on page 92 or "Powering On
DC Switches" on page 97
9
"Verifying the Installation" on page 101
10
"Cabling the Twisted Pair and Fiber Optic Ports" on
page 104
11
"Installing Optional SFP Transceivers" on page 106
Procedure

Advertisement

Table of Contents
loading

Table of Contents