4. Installation

4. Installation

4.1 Scope of delivery and installation

10
The boiler is supplied fully assembled and protected. The boiler
is placed on a pallet (70 x 130 cm, 145 cm high), which can be
transported with a pallet truck, hand truck, forklift truck or 4-wheel
transport boards. The packaging passes through all standard
doors (minimum width of 74.5 cm).
The boiler is installed as follows:
- Position the pallet with the boiler in the boiler room;
- Remove the fixing bands and all other packaging (some
components are packaged in the polystyrene cap);
- Lift the boiler from the pallet;
- Slide the boiler into the required position, using the recessed
handles in the boiler base;
- Cover the boiler and do not operate it whilst dust creating
construction processes or insulation to the pipe work etc. are
carried out in the plant room.