17. Checklists (records)

17. Checklists (records)

17.1 Checklist for commissioning (Commissioning record)

Commissioning work, see Section 9.2
1. Fill the central heating system with water . Check the water pressure in the
central heating system.
2. Fill trap with water.
3. Vent central heating system
4. Check circulation pump operation
5. Check water-side connections for tightness
6. Check type of gas of fered
(Does the type of gas of fered correspond to the type of gas
for which the boiler is suited?)
7. Check the gas supply pressure
8. Check gas meter capacity
9. Check the gas tightness of the connections and the gas pipes
10. Vent gas supply pipe
11. Check electrical connections
12. Air supply and flue gas discharge connections checked
13. Check function and operational status of the boiler
14. Check whether the gas/air ratio control is correct
15. Measuring equipment removed and cap refitted on flue gas measuring point
16. Refit boiler front housing again in the proper manner
17. Write type of gas on the boiler type plate
18. Set room thermostat or boiler control to desired value
19. Instruct user and hand over the necessary documents
20. Confirmation of commissioning
(Company name, signature of engineer)
table 20
Commissioning record

17.2 Checklist for annual inspection (inspection record)

Inspection work, see Chapter 10.
1. Water pressure checked
2. Air supply and
flue gas discharge connections
checked
3. Ignition electrode checked
4. Combustion checked
5. Heat exchanger (central heating)
checked
6. Check the venturi for corrosion
7. Confirmation of inspection
(signature of engineer)
table 21 Inspection record
70
Confirmation and date
Measured value or confirmation
O
O
O
O
O
O Natural gas G20/G25/propane
Wobbe index .......kWh/m
3
O
O
O
O
O
O
O
O
O
O
O
O
O
Date:
GAS 210 ECO PRO
114494-190310

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents