Cassette loading/unloading check
(1)
Articles to be used
(a)
SDA
(b)
DC power supply (+12 V, 5 V)
(2)
Check procedure
(a)
Connect
SDA in accordance with Item 4-2-5,
and set
the POWER
switch to the PSA side (it is not required to connect a
check
cable C).
(b)
Push in the ejector with the finger to bring about the cassette
loading status (Fig.
30'2, 30'3).
(c)
Hake sure that the indicator CLD of SDA lights up.
(d)
Push the eject button to return to the cassette unloading status.
(e)
Hake sure that the indicator CLD of SDA goes out.