Power On Procedure

When powering on the EonStor subsystem, please follow these steps.
Step 1.
Step 2.
Step 3.
4-12
BBU Modules – If BBU module is used, make sure that it has been
installed correctly.
Hard Drives – Hard drives have been correctly installed on the drive
trays.
Drive Trays – ALL the drive trays, whether or not they have a hard
drive, have been installed into the subsystem.
Cable Connections – The iSCSI ports on the subsystem have been
correctly connected to the initiators or the Ethernet network.
Power Cords – The power cords have been connected to the PSU
modules on the subsystem and plugged into power source.
Ambient Temperature – All the subsystem components have been
acclimated to the surrounding temperature.
Power on the network connection devices.
These devices include the Ethernet switches, routers, and any
other such devices that have been connected to the EonStor
S12E subsystem. Please refer to the documentation that came
with your network device to see the power on procedure.
Power on expansion JBODs.
If a multi-enclosure configuration is applied, power on the
expansion enclosures before powering on the managing RAID
subsystem(s).
Power on the EonStor subsystem.
To power on the subsystem please follow the procedures
below.
Using the included power cords, connect both power
sockets on the subsystem's power supplies to the main
power source.
Power on by using the two (2) power switches on power
supplies. (See Figure 4-9 and Figure 4-10) Each switch
controls a single PSU; therefore make sure that both
switches are turned on.