Installing the Server Blade and Options
4. Connect the cable from the battery module to the Smart Array 5i Plus memory
module.
Figure 1-20: Cabling the Battery-Backed Write Cache
Enabler
5. Reinstall the system board and the access panel. Refer to "Preparation
Procedures" in this chapter.
NOTE: Insight Manager 7 will indicate a low charge until the battery module is fully charged
for 24 to 48 hours.
Hot-Plug SCSI Hard Drives and Blanks
The following section explains removal and installation of hard drive blanks and
hot-plug SCSI hard drives.
Removing Hard Drive Blanks
The server blade ships standard with four hard drive blanks. Before installing a
hot-plug SCSI hard drive, you must remove a blank.
1-26
HP ProLiant BL40p Server Blade Setup and Installation Guide