DANGER
If you do not have the optional second power supply, locate the power cord for the
single power supply that is already installed in the machine frame. Insert the power
cord into the power receptacle on the front of the machine. Go to "Installing GBICs".
If you do have an optional second power supply, remove it from its shipping
container.
Look at Figure 11. On your machine, the left power supply location is filled with a
temporary cover. Grasp the cover and pull it forward while holding the machine
firmly. Remove and discard the cover.
Figure 11. 2109 model S16 with two power supplies
To install the optional second power supply, perform the following steps:
1. Look at the back of the power supply; the power supply is installed with the
2. Pull out the handle on the front of the power supply by grasping the handle at
3. Slide the second power supply unit into its slot until it connects into the back
4. Lock the handle into the power supply by pushing the handle back into the
5. Locate the power cords and insert them into the power receptacles on the front

Installing GBICs

The 2109 Model S16 Switch comes standard with four GBICs as shown in
Figure 12 on page 26. Up to 12 additional GBICs are available. GBICs can be
inserted in any port in the switch in any order, including skipping ports.
To prevent a possible electrical shock when installing the device, ensure
that the power cord for that device is unplugged before installing signal
cables. (72XXD204)
Fiber Channel Switch 2109 S16
connector in the down position.
the top and pulling out and down.
panel.
upright and locked position.
of the machine. Go to "Installing GBICs".