Electric Requirements; First Start (Operation Check) - RoboLabs RC800MD Instruction Manual

Conveyor oven
Table of Contents

Advertisement

3.3

Electric requirements

The machine requires 3 phase 400 V 50 Hz five-wire system (L1-L2-L3-N-GND).
Use 3P+N+PE 63 A 400 V pin and sleeve connector (IEC 60309). Short-circuit current rating
for the machine is 6 kA.
The wall receptacle must be connected to a switchboard equipped with a circuit breaker
rated 63 A.
Equipotential bonding wire (up to 10 sq.mm) shall be connected to screw terminal on the base
frame marked with IEC 60417-5021 sign:
Check the voltage in the receptacle. Check the grounding in the receptacle. Plug the
machine in.
Make sure that the supply cord is not twisted, pulled, and is not mechanically impacted in any
other way; and also is not in contact with hot surfaces.
3.4

First start (operation check)

ATTENTION! Machine that was kept for a long time at temperatures below 0 °C must be kept
in normal room temperature (20-22 °C) not less than 12 hours before first start.
Follow these steps to check the machine operation:
1. Press START button, wait for the start screen:
2. Press
to check conveyor operation. Make sure it operates without any side noises.
Press
to stop.
3. Press
to check turbine operation. Make sure it operates without any side noises.
Press
to stop.
11