Changing the pump tubing
For changing the pump tubing please proceed as follows:
1. Unplug the pump from the mains voltage. The device needs to be voltage free.
2.
Open tube connections at the pump;
3. Press conveying belt
4. Take away conveying belt
connectors;
5. Press the two contact pulleys
springs have to be changed (see chapter 19.3.3);
6. Put the new tubing set
Warning
7. Put the conveying belt
8. Press conveying belt at the recessed grips and simultaneously turn the S-bolt
Switch on pump.
9.
Figure 17
Different pump tube sizes
42
S-bolt
2
5
springs
at the recessed grips and turn S-bolt
and remove the old tubing set
and check whether the spring pressure is still sufficient, if not, the contact
with the tube connectors into the guides of the conveying belt
Only the usage of the original tubing set guarantees a proper functionality.
Never lubricate the tube.
Before mounting the pump check all parts for contaminations and clean if necessary.
with the new tubing
CSS-VC-1.6 | 1.02.01
Tubing set
3
clockwise up to limit stop;
from the guides by pulling on the tube
into the dovetail guide of the pump body;
;
anticlockwise until it snaps;