Step 10: Make Ac Power Connections - Tesla Powerwall 2 AC Installation Manual

Hide thumbs Also See for Powerwall 2 AC:
Table of Contents

Advertisement

Step 10: Make AC Power Connections

1. Connect the electrical service from the service inlet or from the main switchboard
(depending on the backup configuration) to the Backup Gateway terminals according to the
following table and diagram (Fig 37). Strip the ends of the wires and insert them in the
corresponding Backup Gateway terminal lugs. Tighten the lugs to the values shown in the
table below.
NOTE: For electrical service connections to the Backup Gateway, use 2.5–50 mm
minimum copper (Cu) wire.
Service Connection
Line 1
Neutral
Wire Gauge
2.5–6 mm
10 mm
2
16–25 mm
25–50 mm
Backup Gateway AC Wiring
Backup Gateway Terminal
S1
N
Backup Gateway Power Terminal Torque Values
2
2
2
Figure 37: Backup Gateway Power Connectors
Wire Gauge
2.5–50 mm
2.5–50 mm
Terminal Lug Torque Value
4.0 Nm
4.5 Nm
5.0 Nm
5.5 Nm
2
, 90 deg C
2
2
35