4.3 Requirements for all power supply and ground cables provided by the
customer
Power supply and ground cables shall be dedicated to the system. They must not be
used to supply other systems.
Power supply and ground cables shall be kept separated from room system cables.
Power supply and ground cables must be connected to the same distribution panel.
They must run near one to the other.
Power supply and ground cables provided by the customer shall be compliant with
local regulations (UL, CSA, IEC, CCC).
Power supply and ground cables must be CCC certified and labeled for installation in
China.
Reference: For specific Vascular system grounding maps and connection details, refer to the
MisMap and mis chart listed in
Chapter 6 Electrical Connections
Section 14,
MIS (Master Interconnect System).
Direction 5314528-2-1EN, Revision 1
167