4.3 Requirements for all power supply and ground cables provided by the
customer
•
Power supply and ground cables shall be dedicated to the system. They must not be
used to supply other systems.
•
Power supply and ground cables shall be kept separated from room system cables.
•
Power supply and ground cables must be connected to the same distribution panel.
They must run near one to the other.
•
Power supply and ground cables provided by the customer shall be compliant with
local regulations (UL, CSA, IEC, CCC).
•
Power supply and ground cables must be CCC certified and labeled for installation in
China.
Reference: For specific Vascular system grounding maps and connection details, refer to the
MisMap and mis chart listed in
Chapter 6 Electrical Connections
Section 14,
MIS (Master Interconnect System).