f.
Connect the Fluoro UPS rectifier input cable from PDB CB5 as follows (
6-32
g. Connect the Fluoro UPS output cable from PDB power block 2 as follows (
6-32
2. Tie the power cables to the UPS and place the protection plates back on the UPS.
17.4 Finalization
No finalization steps.
200
):
•
Rectifier input phase 1 to X1-L1-1 terminal,
•
Rectifier input phase 2 to X1-L2-1 terminal,
•
Rectifier input phase 3 to X1-L3-1 terminal,
•
Rectifier ground to X1-PE-rectifier terminal.
):
•
Output load 1 to X1- L1 terminal,
•
Output load 2 to X1-L2 terminal,
•
Output load 3 to X1-L3 terminal,
•
Output load neutral to X1-N-Load terminal.
•
Ground to X1-PE-Load terminal.
Direction 5314528-2-1EN, Revision 1
17 PIST0021 - US Fluoro UPS and PDB connection