Power And Grounding Requirements; Requirements For Ground Cables Provided By The Customer; Requirements For Power Supply Cables Provided By The Customer - GE Innova 2100-IQ Preinstallation Manual

Cardiovascular imaging system
Hide thumbs Also See for Innova 2100-IQ:
Table of Contents

Advertisement

Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare

4 Power and Grounding Requirements

4.1 Requirements for ground cables provided by the customer

A wall circuit breaker or equivalent device with LOTO capability must be installed on
the Main Power. This device must be compatible with the power input specifications
of the system. Procurement, delivery and installation of this breaker is customer
responsibility.
The customer shall provide the ground wire between the EMI filter (for Fluoro UPS
CE option only), PDB (Power Distribution Box) and earth. Impedance of the ground
wire to earth shall be lower than 2 ohms (refer to direction 46–019668 for method of
measurement).
The ground wire to earth shall be a minimum of AWG 2/0 (UL) or 35 mm 2 (CE) or the
same size (100%) as feeder wires, which ever is larger.
The shield of any shielded cable coming from the distribution cannot replace the
ground wire.

4.2 Requirements for power supply cables provided by the customer

The customer shall provide the power supply cables between the main transformer and the
system:
between the transformer and the PDB (Power Distribution Box),
between the transformer and the EMI filter (for Fluro UPS CE option only),
between the EMI filter and the PDB (Power Distribution Box) (for Fluro UPS option
only) (max length = 3 m),
between the PDB and the Jedi (max length = 24 m),
between the PDB and the C1 cabinet (max length = 24 m),
between the PDB and the tube chiller (max length = 24 m),
between the PDB and the Fluoro UPS (Fluoro UPS option).(max length = 24 m),
between C1 and C2 cabinets (max length = 6 m)
The power supply cable between the main transformer and the PDB (Power Distribution Box)
and between the PDB and the Jedi shall be sized to insure proper voltage drop.
Table 6-3:
V
The power supply cables provided by the customer shall be sized according to the
Illustrations AC Interconnect without Fluoro UPS and AC Interconnect with Fluoro UPS
in
Section 1,
166
Max Line Impedance for feeder line between Generator cabinet and Hospital
380
400
0.09
0.096
Power Distribution.
Direction 5314528-2-1EN, Revision 1
420
440
0.102
0.108
4 Power and Grounding Requirements
460
480
0.114
0.12

Advertisement

Table of Contents
loading

This manual is also suitable for:

Innova 3100Innova 3100-iqInnova 4100Innova 4100-iq

Table of Contents