Step 1: Position The Iq Cable; Step 2: Position The Junction Box; Step 3: Mount The Microinverters - enphase IQ8 Series Installation And Operation Manual

Microinverters
Hide thumbs Also See for IQ8 Series:
Table of Contents

Advertisement

Step 1: Position the IQ Cable

A. Plan each cable section to allow connectors on the IQ Cable to align with each PV module. Allow
extra length for slack, cable turns, and any obstructions.
B. Mark the approximate centers of each PV module on the PV racking.
C. Lay out the cabling along the installed racking for the AC branch circuit.
D. Cut each section of cable to meet your planned needs.
WARNING: When transitioning between rows, secure the cable to the rail to prevent cable
damage or connector damage. Do not allow the connector at the microinverter to be under
tension, ensure the bend radius is 50 mm for single-phase and 60 mm for three-phase.

Step 2: Position the junction box

A. Verify that the AC voltage at the site is within range.
Single-phase service
L1 to N
*Nominal voltage range can be extended beyond nominal if required by the electricity network operator.
B. Install a junction box/AC isolator/installation coupler at a suitable location.
C. Provide an AC connection from the junction box/AC isolator back to the electricity network using
equipment and practices in accordance with local electrical codes and standards.
D. For single-phase installation, verify IQ Cable wiring colour codes are correctly terminated: L1-
Brown, N-Blue
E. For multi-phase installations, verify the IQ Cable wiring colour codes are correctly terminated: L1-
Brown, L2-Black, L3-Grey, N-Blue.
WARNING: Blue conductor in IQ Cable should be used only for
neutral connection. Incorrect termination may irrecoverably
damage any connected microinverters.

Step 3: Mount the microinverters

A.
he microinverters should be mounted beneath the modules either horizontal bracket side up or
T
vertical orientation to the module and must be protected from direct exposure to rain, UV, and other
harmful weather events. Please refer to the image below for clearance requirements during vertical
mounting.
Always place the microinverter under the PV module, protected from direct exposure to rain,
sun, and other harmful weather events. Allow a minimum of 19 mm (3/4") between the roof and
the microinverter. Also, allow 13 mm (1/2") between the back of the PV module and the top of
the microinverter.
For vertical mount, also maintain at least 300 mm (12") clearance from the edges of the PV
module to protect the microinverter from direct exposure to rain, UV, and other harmful weather
events.
WARNING: Install the microinverter under the PV module to avoid direct exposure to rain, UV, and
other harmful weather events. Do not mount the microinverter upside down.
15
184 to 276 VAC*
© 2023 Enphase Energy Inc. All rights reserved.
IQ8AC/IQ8HC Installation and Operation Manual
Multi-phase service
L1 to L2 to L3
L1, L2, L3 to N
319 to 478 VAC*
184 to 276 VAC*
L3
N
L2
L1
June 2023
USM-00005-2.0