WAGNER PER-X1 Translation Of The Original Operating Manual page 49

Robot powder spray gun
Table of Contents

Advertisement

Section
Type of inspection
6
Ground leaking resistance
from the work piece attach-
ment point
7
Measures to take if the work
pieces are insufficiently
grounded
8
Effectiveness of the manu-
ally or automatically actu-
ated fire extinguishing sys-
tems (room protection sys-
tem)
Requirements
The ground leaking resistance of the attachment
point of every work piece may be 1 megohm at
most (measuring voltage must be 500 V or
1000 V). The design of the work piece holder
must ensure that the work pieces remain
grounded during coating.
If sufficient work piece grounding in accordance
with section 6 cannot be ensured, appropriate
equipment, e.g., ionizers, must be used to dis-
charge electric charges on the work piece. Such
equipment must not exceed the permitted dis-
charge energy of the spraying systems with
which it is used. In terms of permitted discharge
energy, this equipment must be put through the
same inspections as the powder spraying sys-
tems used with it. The discharge equipment
must be interlocked with the spraying system
such that the high voltage is switched off and
that coating cannot take place if the discharge
equipment malfunctions.
Effectiveness of the manually or automatically
actuated fire extinguishing systems (room pro-
tection system).
Inspection
Type of inspection
by
SP
ME/CM
Measure the ground leaking resis-
tance (ground potential of the
workpiece mount)
maximum 1 MOhm @ 500 V/1000
V.
SP
ME/FT/CI
Measurement of discharge energy,
check the monitoring equipment's
test function by triggering it.
MFR/FPE
FT
Trigger fire extinguishing system,
observe manufacturer's require-
ments.
Inspection in-
terval
Weekly
Weekly
6 months