Chemicals For The Operating The Machine; Instructions For Disposal Of Packing Material; Settings For Initial Commissioning By The Service Engineer; Commissioning - Meiko UPster H 500 Operating Instructions Manual

Dishwashing machine
Table of Contents

Advertisement

Operating Instructions UPster H 500 / H 500S
CAUTION!
CAUTION!
9735020
6.8

Chemicals for the operating the machine

Only alkali detergents and acid rinse agents suitable for use in commercial ware-
washing machine may be used. Relevant information is provided by the manufactur-
ers of these products.
MEIKO recommends brand cleaning products from leading manufacturers. - clean-
ing and hygiene products
ucts can considerably reduce the service life of the dosing units. Observe the manu-
facturers' dosing instructions.
Detergents and rinse aids can present a health hazard if they are not correctly used.
Observe the manufacturers' indication on the original containers and safety data
sheets.
"Items for rinsing are tribologically influenced in particular by chemicals and in-
creased temperatures during the process, as well as mechanical stresses caused by
handling and transporting."
If a descaling agent is used, please strictly observe the manufacturer's handling and
safety instructions. After having used such an agent, the product must be completely
removed from the machine, as even small residues are sufficient to destroy plastic
parts and packing materials.
Chemical product settings
The correct settings for the quantity of detergent and rinse aid depend on the product
used. The relevant chemical product supplier can install the correct setting.
6.9

Instructions for disposal of packing material

 The four-sided wooden frame consists of untreated, raw wood.
 Special country-specific import regulations may also stipulate the use of wood which
has been treated against pests.
 The plastic sheeting (PE sheeting) can be recycled.
 The cardboard packaging material used to protect the edges can also be recycled.
 The steel strap from the packaging can be recycled as steel scrap.
 The plastic tensioning strap (PP) can be recycled.
7
Settings for initial commissioning by the service engi-
neer
7.1

Commissioning

To avoid damages or dangerous injuries during the setting in operation of the washing
machine, please observe the following points:
Perform any required initial checks on supplied parts. More detailed information, if re-
quired, can be found in the relevant operating instructions.
The warewashing machine may only be commissioned by suitably qualified
persons observing the safety instructions.
Before the first start, check if all tools and foreign parts are removed out of the
installation.
Check any escaped fluids have been removed.
Activate all the safety systems and hood switch before commissioning.
Check that all screw connections are tight.
Please also read the chapter "General safety instructions".
Commissioning and training will be handled and provided by MEIKO-trained
service engineers. The operator must not use the installation before completing
training.
Design and construction subject to change without prior notice!
Page
are an excellent choice. Using unsuitable prod-
14
42
of

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Upster h 500s

Table of Contents