5.7
5.8
Only alkali detergents and acid rinse agents suitable for use in commercial dishwashers
may be used. Corresponding information is submitted by the manufacturers of such
products.
IMPORTANT!
MEIKO recommends brand cleaning products from leading manufacturers. - cleaning
and hygiene products are an excellent choice.
If unsuitable products are used, the life expectancy of the dosing units can be reduced
considerably.
Observe the dosing instructions of the manufacturer.
Detergents and rinse-aids can present a health hazard if they are not correctly used.
Please observe the manufacturers' instructions on the original packing and on the
safety data sheets.
"Items for rinsing are tribologically influenced in particular by chemicals and increased
temperatures during the process, as well as mechanical stresses caused by handling
and transporting."
If a de-scaling agent is used, please strictly observe the manufacturer's instructions reg.
handling and safety. After having used such an agent, the product must be completely
removed from the machine, as even small residues are sufficient to destroy plastic parts
and packing materials.
Chemical product settings
The correct settings for the quantity of detergent and rinse agent depend on the product
used.
The relevant chemical supplier can install the correct setting.
6
6.1
In order to avoid damage to the installation and the injury and death of persons when com-
missioning the installation, the following points must be observed without fail:
Any necessary initial tests to parts supplied by sub-suppliers must be carried out. More
detailed information, if required, can be found in the relevant operating instructions.
IMPORTANT!
7
The appliance must not be used without a thorough knowledge of the "Operating
Instructions". Incorrect operation could result in injuries to personnel or damage to
the appliance.
IMPORTANT!

Emergency-off

Switch the machine off completely via the on-site power disconnection device.

Chemicals for the operation of the appliance

Settings for initial commissioning by the service engi-
neer

Commissioning

The installation may only be commissioned by suitably qualified persons observing
the safety instructions.
Before initial startup, check that any tools and parts not belonging to the installation
have been removed.
Check whether any escaping liquid is removed.
Activate all the safety systems and hood switches before commissioning.
Check that all screw connections are tight.
Please also read the chapter on "General safety instructions ".
Commissioning and instructions will be provided by technicians specially trained
by Meiko. The operator may only use the installation after training has been pro-
vided.
The "Commissioning certificate for GiO modules" is to be observed for machines
equipped with the GiO module and the instructions adhered to accordingly.

Washing with dish-washer

13 / 44