f. Align the front of the rail with the holes on the rack posts that will receive the rails and pull the rail toward the
holes until the latching mechanism engages the rack. If necessary, unscrew the rack post fasteners to enable the
latching mechanism to engage. Screw the rack post fasteners back into the proper holes.
g. Use a level to make sure that the rails are aligned properly.
h. Follow these steps for the other outer rail.
CAUTION
Always install the top cover onto the enclosure before installing the chas-
sis into a rack. Not having the top cover installed may damage the align-
ment brackets.
Step 5 : Install the rail mounting hardware, starting with the uppermost rack mounting hole of the 4U space on
the front of the rack.
CMA Standard:
a. Install one cagenut at the uppermost mounting hole of
the 4U space that the enclosure will occupy.
b. If the VTrak J5960 will be installed in a rack for shipping
purposes, install four more M5 cage nuts in the holes 3-6 of
the 4U space. These will receive the M5 x 12mm T15 Flat
Head Torx screws that secure the enclosure to the rack with
the shipping bracket.
Cage Nut Spacing