SolarEdge Energy Bank Installation Manual page 65

Home hub inverter single phase for australia
Hide thumbs Also See for Energy Bank:
Table of Contents

Advertisement

64
  Power Optimiser Troubleshooting
Malfunction
PV string Voltage is higher than
number of Power Optimisers
WARNING!
If the measured voltage is
too high, the installation may
not have a safe low voltage.
PROCEED WITH CARE! A
deviation of ±1% per PV
string is reasonable.
Possible Cause and Corrective Action
Extra Power Optimiser(s) connected in the PV
string (not applicable to smart modules).
Check if an extra Power Optimiser is connected
in the PV string. If not – proceed to next solution.
A module is connected directly to the PV string,
without a Power Optimiser (not applicable to
smart modules).
Verify that only Power Optimisers are connected
in the PV string and that no module outputs are
connected without a Power Optimiser. If the
problem persists, proceed to the next step.
Power Optimiser(s) malfunction.
 1. Disconnect the wires connecting the Power
Optimisers in the PV string.
 2. Measure the output voltage of each Power
Optimiser to locate the Power Optimiser that
does not output 1V safety Voltage. If a
malfunctioning Power Optimisers located,
check its connections, polarity, module, and
Voltage.
 3. Contact SolarEdge Support. Do not continue
before finding the problem and replacing the
malfunctioning Power Optimiser. If a
malfunction cannot be bypassed or resolved,
skip the malfunctioning Power Optimiser,
thus connecting a shorter PV string.