  Step 2: Connecting a PV module to a Power Optimiser

Step 2: Connecting a PV module to a Power Optimiser

NOTE
Improper wiring may cause electrical faults in a PV system. To avoid electrical
faults, verify proper locking of connectors and avoid cable tension and friction.
Proper planning, materials and installation reduce the risk of electric arcs,
short-circuits and ground faults in the PV system.
NOTE
Images are for illustration purposes only. Refer to the label on the product to
identify the plus and minus input and output connectors.
For each of the Power Optimisers:
Connect the Plus (+) output connector of the module to the Plus (+) input connector
of the Power Optimiser.
Connect the Minus (-) output connector of the module to the Minus (-) input
connector of the Power Optimiser.
Figure 2: S-Series (left) and P-Series (right) Power Optimiser connectors
SolarEdge Home Hub Inverter Single Phase MAN-01-00812-1.5