Installing Battery Cables - Huawei UPS2000-G-6KRTLL User Manual

Hide thumbs Also See for UPS2000-G-6KRTLL:
Table of Contents

Advertisement

UPS2000-G-6KRTLL
User Manual
----End

3.5.2 Installing Battery Cables

Prerequisites
● When installing a power cable to the lithium battery, ensure that the
● Do not connect two or more cables to the positive or negative power port of
Figure 3-5 Installing battery power cables
Procedure
Step 1 Remove the battery terminal covers.
Step 2 Connect the PE cable to the cabinet ground bar.
Issue 02 (2022-06-30)
NO TE
K
indicates the general AC input circuit breaker, Q indicates the general AC output circuit
m
breaker, and K
indicates the battery circuit breaker.
b
CA UTION
protruding part of the OT terminal on the cable faces outwards.
the lithium batteries in parallel.
NO TE
● The UPS2000-G-6KRTLL needs to connect to external lithium batteries. Each UPS
supports a maximum of 16 batteries connected in parallel. This document uses four
lithium batteries connected in parallel as an example.
● If the UPS connects to only one lithium battery, the maximum load power is 4.0 kW.
● When lithium batteries are connected, it is recommended that a DC circuit breaker (150
A/80 V DC circuit breaker for the 6 kVA UPS) be installed between the lithium batteries
and the UPS.
● Before connecting cables to the UPS, ensure that the battery circuit breakers are OFF to
prevent operations with power on.
● If the UPS connects to multiple batteries, configure the PE bar and battery busbar.
● If busbar terminals are insufficient, cascade the busbars.
● Busbar dimensions (H x W x D): 76 mm x 465 mm x 70 mm