OPERATORS MANUAL
Section 3: Processing Solutions
Preparing the Solutions
Processing Tanks with the Splash Guard
Figure 6
and the Drip Tray
DRIP TRAY
Draining the Tanks
Warning
• All drain material must be made of chemically resistant, non-corrosive material. Use PVC or the equivalent. The
Drain must have a minimum diameter of 7.6 cm (3 in.) and no obstructions. See the Site Specifications,
Publication No. 7C8769.
• Relatively small amounts of fixer can seriously contaminate the developer. If solutions are changed in both
Tanks, fill the fixer Tank first so that any solution spilling into the developer Tank can be thoroughly cleaned.
• Drain only one Tank at a time.
8
SPLASH GUARD
H172_1003ACA
H172_1003AC
Refer to Service Bulletin 30, Part No. 632661, for more
information.
Caution
• Avoid contamination of the processing solutions.
• To avoid spilling solutions from one Tank into the
next one, use the Splash Guard between the
developer and fixer Tanks.
• Slowly install or remove the Racks.
• Use the Drip Tray when moving Racks to or from
the Processor.
• Do not mix more than a 2-week supply of
chemicals.
[1] Mix the volume of processing solution required in
the correct replenisher Tank. Use the instructions
packed with the chemicals to mix the solution.
Note
[2] Remove the Crossover Assembly and the Rack
from the Tank that is to be filled.
19JAN99 – 7C8770