Centralized Or Distributed Architecture Connections; Multiple-Cabinet Installations; Special Requirements; Centralized Architecture - ABB Galaxy Power System Installation Manual

Table of Contents

Advertisement

6. Centralized or Distributed Architecture Connections

Multiple - Cabinet Installations

Special Requirements

This section covers the special requirements for multiple-cabinet installations. These are:
·

Centralized Architecture

DC power connections to central bus bar

Remote voltage sense (regulation) and system shunt for the Galaxy Power System controller
·
Distributed Architecture
Inter cabinet dc power bus connections
·
All Types
Inter cabinet alarm and serial bus connections
Centralized Architecture

Introduction

This section covers the field assembly for Centralized Architecture
DC power connections to central bus bar
Refer to Figure 6 - 1 for this procedure
Step
1
Install optional plates if more than 8 connections are needed. (See Figure 6 - 1.)
Run and connect new wires from positive and negative bus bars in each cabinet to charge and charge return
centralized bus bars located outside the equipment.
2
Note: In centralized architectures all return wires from the load must be terminated to the external discharge
return bus. These return wires may not be terminated in the cabinet.
Page 36
© Copyright 2021 ABB. All rights reserved.
DC power connections to central bus bar
Action

Advertisement

Table of Contents
loading

This manual is also suitable for:

Gps 4848/100Gps 4827Gps 4830Gps 434

Table of Contents