Step
To turn on the system while using the factory default firmware and software loaded in the controller, proceed as
follows:
Before proceeding with the initial power up of the system, verify:
·
Batteries are disconnected from the system bus.
·
The ac source circuit breakers are turned OFF.
·
The system ac and dc load circuit breakers/fuses are OFF or removed.
Note: Install rectifiers from bottom to top of GPS 4848 cabinets. GPS 4830 rectifiers are installed, starting from
the top-left and working right, then down. GPS 4827 rectifiers are installed, starting from the bottom-left
and working right, then up. Vacant rectifier positions below or beside the top installed rectifiers in a GPS
4848 cabinet may cause over-heating of the installed rectifiers. Install a Rectifier Shelf Cover / Air Dam into
vacant positions.
Install Rectifier Shelf Cover / Air Dam on rectifier shelves as required. See Figure 13-2A.
When installing a single 595LTA or 595LTB on a shelf, install an Air Dam to block vacant right or left rectifier
position.
Rectifier Shelf Cover (848680211) - Covers both left and right rectifier positions
Air Dam (848754358) - Covers the left or right rectifier position
Page 133
© Copyright 2021 ABB. All rights reserved.
Initial Power Up of the System
Action
Warning

Advertisement

Table of Contents
loading

This manual is also suitable for:

Gps 4848/100Gps 4827Gps 4830Gps 434

Table of Contents