Bay ID and Shunt Size Configuration

BLJ2/3 (Millennium II Controller)

Refer to Figure 6 - 9 for this procedure.
Step
Set the DIP switches S1.1, S1.2, S1.3, S1.7, & S1.8 on the BLJ2/3 board for the bay ID number. (Factory default is Bay 1.)
Set DIP switches S1.4, S1.5, & S1.6 on the BLJ2/3 board per the Table below to configure the shunt size for the 4 shunt
circuits of the BIC9.
Note: All shunt circuits wired to the BLJ2/3 must be at the same bus potential and must have 100K ohm CLRs (Current
Limiting Resistors) installed at the shunt end of the circuit. If the shunts to be monitored are at return bus
potential instead of hot bus potential, then jumper J12 (immediately above S1) must be moved to the 2 - 3
position.
If the Software Configured Shunt Size is selected, proceed to the next section on configuration of it using the
Millennium II controller web pages.
Page 50
© Copyright 2021 ABB. All rights reserved.
BLJ2/3 (Millennium II Controller)
Figure 6-9: BLJ2/3 DIP Switch Settings When Using a Millennium II Controller
Action
BICJ/BIC9 Shunt Circuits
J12

Advertisement